We will be in the space this month at some point (whether it's 100% done or not). :)
Remaining projects by us include:
-door install
-trim around doors
-wainscoting master bath
-baseboards
-closet systems
-electrical (over 1/2 way done with fixture/switch/outlet install
-door hardware
-window hardware
-paint halls, master, master bath, office
-paint trim
-2 coats poly on banister
-get final permits approved
-smoke/carbon monoxide alarms up
Projects by subs:
-finish tile (over 1/2 way done)
-shower glass (templating tomorrow)
-caulk marble counters in master
-install master toilet/faucets
-install shower plumbing hall bath
-finish baseboards on built ins
-spray paint doors and possibly built ins.